- EXISTING CONDITIONS
- * June 1972 inundation
- * 100-year inundation
|
|
2
|
|
|
3
|
|
|
4
|
- Flow Frequency Analysis
- * Peak Flow Frequency on the Susquehanna River
- - 100-year discharge = 260,000 cfs
- * Peak Flow Frequency on Fishing Creek
- - 100-year discharge = 47,400 cfs
- * Results Compare with 1979 FEMA FIS
- - COE 100-year discharge on Susquehanna River is 5% lower than FEMA
FIS
- - COE 100-year discharge on Fishing Creek is 19% lower than FEMA FIS
|
|
5
|
- HEC-RAS Model
- * Used surveyed stream cross sections
|
|
6
|
|
|
7
|
|
|
8
|
|
|
9
|
|
|
10
|
- HEC-RAS Model (cont.)
- * Assumed railroad mitigation bridge and Rt. 44 (Double Track) bridges
remain
- * Modeled 2, 5, 10, 25, 50, 100,200, 500- year
and June 1972
- * Modeled 4 project alternatives and existing conditions
|
|
11
|
|
|
12
|
- HEC-RAS Model (cont.)
- * Without project
- * Interior alignment
- * Fringe without Fernville
alignment
- * Fringe with Fernville alignment
- * 5 and 10 foot depth dredging
|
|
13
|
|
|
14
|
|
|
15
|
- Top of Protection
- * Used results of HEC-RAS model to set top of protection profile
- * Performed a risk and
uncertainty analysis to take into account:
- - uncertainty in flow frequency
- - contraction and expansion coefficients
- - debris at bridges
- - roughness of channel and floodplain
|
|
16
|
- Top of Protection (cont.)
- * 100-year with-project water surface elevations vs. June 1972
with-project water surface elevations along Fishing Creek
- - 100-year higher than June 1972 upstream of Reading Railroad Bridge
- - June 1972 is a 440-year event on Susquehanna River
- - June 1972 is a 53-year event on Fishing Creek
- - Top of protection set to highest event to provide at least 100-year
protection throughout community
|
|
17
|
- Interior Flooding
- * Area behind Bloomsburg alignment
- - Preliminary analysis using computer model HEC-IFH
- - Divided into 4 subbasins
- - Two conditions: blocked or unblocked drainage structures
- - 10, 25, 50, and 100- year storm events analyzed
- - Some interior flooding still remains with project
- * Area behind Fernville alignment
- - Preliminary analysis using
existing mapping
- - provided 5-24 drainage structures thru levee
|
|