1
 
2
Environmental
What We Will Cover
  • Environmental resources
  • River and Creek
  • Wetlands
  • Wildlife & Fish
  • Agricultural Lands (including Prime and Unique)
  • Sediment and Erosion Control/Water Quality
  • Potential contamination issues


3
Cultural
What We Will Cover
    • McClure House
    • Magee Mansion
    • Fair Week
    • Fairgrounds
    • PA Canal, Lock and Lock Tender’s House
    • Water Treatment Plant Building and Pump
    • Boone’s Dam
    • Remaining Archeological Resources
    • Remaining Process
4
Environmental Resources
  • Susquehanna River
  • Warm Water Fishery
  • Several ecosystem stressors (AMD, other pollution)
  • Other encroachments over time
  • Still in moderate condition by PA (not impaired)
  • Little impact from project on floodplain or channel


5
Environmental Resources
  • Fishing Creek
  • Managed by PAF&BC as warm water fishery in lower segment, Trout waters upstream of Light Street
  • ½ mile of lower segment being riprapped
  • Impacted similarly by the WPA project in the late 30’s
  • Construction along either bank, trying to avoid creek impacts, some along edge of creek, both banks
  • Mitigation needed for Impact to creek ecosystem


6

Environmental Resources
  • Wetlands
  • Several types (forested, emergent, shrubby)
  • Several functions (WQ, Flood attenuation, etc.)
  • Impact to emergent wetlands by Fairgrounds (0.7 acres)
  • Impact to forested wetlands along Fishing creek-approximately 2 acres
  • Mitigation needed-Avoid, minimize, compensate
  • Agencies have conducted field visits
  • Goal is to replace lost functions
7
Environmental Resources
  • Fish and Wildlife
  • Have coordinated project with USFWS, PFBC and PAGC as well as other agencies on the ground.
  • Typical F&W resources in project area
  • No threatened or endangered species
  • Goal is then to minimize overall disruption
  • F&W corridors and habitat will experience some impacts (noise, sedimentation, thermal)
  • USFWS and others will comment on DEIS
8
Environmental Resources
  • Agricultural Lands
    • Impacts- Approx. 12 acres of Tioga soils
    • Coordinating with NRCS office-Ag Rating Form
    • Minor impacts to current agric. operations


9
Environmental Resources
  • Sedimentation and Erosion Control
    • PADEP Requirements will be used
    • E&S plan and permit will be obtained prior to construction
    • Temporary increase in turbidity during construction


10
Environmental Resources
  • Presence of Potentially Contaminated Material
    • EPA and PADEP regulations apply
    • An initial round of testing has been done
      • Some contaminated material has been identified near the old landfills
    • Additional, focused testing will be conducted at beginning of the design phase
  • Some potential that the alignment will be adjusted near old landfills (to avoid contaminated soil and debris), primarily due to geotechnical requirements.
  • Low risk to community.
11
Cultural Resources
  • Above ground and below ground resources
  • Historic structures- 500 year floodplain
    • McClure House, Magee Mansion, Water treatment plant, etc.
  • Archaeological resources
    • Arrowheads, shards, canal, lock and house, other foundations
    • Cultural compliance work continues
    • Phase I, II and III
    • Partly through Phase I-PHMC (SHPO)
    • Low risk to resources and project
12
Cultural Resources
  • District anticipates no adverse effect on cultural resources
  • Field work to be done in March-May timeframe
  • Phase I work will determine need for any Phase II
  • Phase II would be done just after Phase I
  • McClure House-No impact
  • Magee Mansion-No impact